6 heritage conservation conditions imposed by Central Coast across 4 development applications in our dataset. Heritage conservation conditions protect items and areas of heritage significance — heritage impact statements, archival photographic recording, conservation works and use of sympathetic materials.

Condition 5 DA/1200/2024 det. 11/09/2025 Alterations & Additions to Existing School

5. PRIOR TO ISSUE OF ANY OCCUPATION CERTIFICATE FOR ALL STAGES 5.1. All conditions under this section must be met prior to the issue of any Occupation Certificate. 5.2. Obtain the Section 307 Certificate of Compliance under the Water Management Act 2000 for water and sewer requirements for the development from Central Coast Council as the Water Supply Authority, prior to issue of the Occupation Certificate. 5.3. Complete construction of all works approved in the Local Government Act Section 68 Stormwater Drainage Works Approval. Completion include the submission and acceptance by Council of all work as executed drawings plus other construction compliance documentation and payment of a…

Condition 5 DA/1200/2024 det. 11/09/2025 Alterations & Additions to Existing School

5. PRIOR TO ISSUE OF ANY OCCUPATION CERTIFICATE FOR ALL STAGES 5.1. All conditions under this section must be met prior to the issue of any Occupation Certificate. 5.2. Obtain the Section 307 Certificate of Compliance under the Water Management Act 2000 for water and sewer requirements for the development from Central Coast Council as the Water Supply Authority, prior to issue of the Occupation Certificate. 5.3. Complete construction of all works approved in the Local Government Act Section 68 Stormwater Drainage Works Approval. Completion include the submission and acceptance by Council of all work as executed drawings plus other construction compliance documentation and payment of a…

Condition 4 DA/683/2024 det. 10/12/2025 Industrial - Metal Recycling Plant

4. DURING WORKS 4.1 All conditions under this section must be met during works. (GL013) 4.2 The principal certifier must ensure that building work, demolition or vegetation removal is only carried out between: 7.00 am and 5.00 pm on Monday to Saturday The principal certifier must ensure building work, demolition or vegetation removal is not carried out on Sundays and public holidays, except where there is an emergency. Unless otherwise approved within a construction site management plan, construction vehicles, machinery, goods or materials must not be delivered to the site outside the approved hours of site works. Note: Any variation to the hours of work requires Council’s approval. GL014…

Condition 6 DA/683/2024 det. 10/12/2025 Industrial - Metal Recycling Plant

6. ONGOING 6.1. Comply with all requirements in the Environmental Protection Licence (EPL) from the NSW Environmental Protection Authority for the activity. Operate and manage the site in accordance with the EPL. 6.2 Comply with and implement all impact mitigation recommendations and measures outlined in the submitted Environmental Impact Statement (Baker Ryan Stewart, April 2024) and ecological impact mitigation measures outlined in Section 6 of the supporting Biodiversity Development Assessment Report (Narla Environmental, October 2025) and tree protection measures outlined in the supporting Arboricultural Impact Assessment (Blues Bros Arboriculture, July 2025). Where the recommendations…

DA/1629/2024 det. 18/09/2025

Provide certification to that effect. 2.15. Submit an application to Central Coast Council for a Road Opening Permit. 2.16. Obtain a Section 68 approval from Council under the Local Government Act 1993 to alter the existing private sewer pump station. 2.17. Implement the recommendations of the Aboriginal Archaeological Due Diligence Assessment Report, prepared by Virtus Heritage, and dated 27 May 2025. 2.18. The attached General Terms of Approval issued by WaterNSW do not constitute an approval under the Water Management Act 2000. The development consent holder must apply to WaterNSW for a Water Supply Work approval before the commencement of any dewatering activity. 2.19. Prior to the…

DA/320/2024 det. 12/12/2024

Maximum Penalties under NSW Environmental Laws include fines up to $1.1 Million and/or custodial sentences for serious offences. ADVISORY NOTES It is an offence under the Biodiversity Conservation Act 2016 to harm protected native wildlife. If during works fauna is displaced, it must not be harmed. If required works will cease and fauna will be transferred to the nearest veterinary hospital and Councils Ecologist will be notified within 24hrs. Discharge of sediment from a site may be determined to be a pollution event under provisions of the Protection of the Environment Operations Act 1997. Enforcement action may commence where sediment movement produces a pollution event. The following…