Newcastle Flood Management Conditions

6 flood management conditions imposed by Newcastle across 3 development applications in our dataset. Flood management conditions address building on flood-prone land — minimum habitable floor levels, flood-compatible materials and construction, evacuation planning and protection of overland flow paths.

Condition 6 MA2024/00006 det. 13/11/2024 Sec 4.55(2) modification to DA2019/01150

6. The proposed floodlighting of the premises is to be designed, positioned, and installed, including appropriate shielding and orientation of the lighting fixture, as to not give rise to obtrusive light, interfere with traffic safety or detract from the amenity of surrounding properties in accordance with Australian Standard 4282:1997 - Control of the obtrusive effects of outdoor lighting. Full details are to be included in the documentation for a Construction Certificate application.

Condition 6 MA2024/00006 det. 13/11/2024 Sec 4.55(2) modification to DA2019/01150

6. The proposed floodlighting of the premises is to be designed, positioned, and installed, including appropriate shielding and orientation of the lighting fixture, as to not give rise to obtrusive light, interfere with traffic safety or detract from the amenity of surrounding properties in accordance with Australian Standard 4282:1997 - Control of the obtrusive effects of outdoor lighting. Full details are to be included in the documentation for a Construction Certificate application.

Condition 59 DA2023/01154 det. 18/03/2025 Residential flat building

59. Flooding - caution signage Before the issue of an occupation certificate, a clear warning notice is to be erected and maintained at all points of entry to the site advising, that the premises is subject to flooding and that caution should be observed at times of heavy or prolonged rainfall. Such notice is to also provide advice regarding the availability of further information sources in respect of possible flooding. Condition reason: to protect the public from floodwaters.

Condition 65 RE2024/00002 det. 28/10/2024 Section 8.2 Review

65. Development applications for each stage shall be accompanied by a Stormwater Management Plan which includes details of connections to the existing drainage infrastructure, any infrastructure upgrades and details of stormwater harvesting for re- use within the development. Calculations to show the stormwater harvesting volumes proposed to meet the requirements of NDCP 2012 for retention volume shall also be detailed on the plans. Flood Mitigation

Condition 19 DA2023/01154 det. 18/03/2025 Residential flat building

19. Flooding - verifying floor levels Before the issue of a construction certificate, full details are to be provided demonstrating that the floor level of all proposed buildings or building additions are to be no lower than 3.6 m Australian Height Datum. Condition reason: to require verification of proposed floor level heights.

Condition 67 RE2024/00002 det. 28/10/2024 Section 8.2 Review

67. A flood assessment prepared by a qualified hydraulic engineer shall accompany the development application for each stage of the project. Surrender of consent

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.