City of Parramatta Bushfire Protection Conditions

3 bushfire protection conditions imposed by City of Parramatta across 3 development applications in our dataset. Bushfire protection conditions apply to bushfire-prone land — asset protection zones (APZ), Bushfire Attack Level (BAL) construction standards, dedicated water supply for firefighting and emergency access.

Condition 33 DA/356/2025 det. 22/01/2026 residential flat buildings

33. Prior to the release of the relevant Construction Certificate(s) the applicant shall submit for the approval of Council’s Group Manager Development and Traffic Services Unit (DTSU), key cross sections, partial plans and partial elevations through external walls, balconies, pergolas and other key external details. Drawings are to be fully annotated at a scale of 1:50 (or if necessary 1:20) showing details, materials, finishes and colours, so that the details and materiality of the external facades are clearly documented. Revised 3D photomontages must also be submitted. The development shall be completed in accordance with the plans approved to satisfy this condition. Reason: To ensure…

Condition 40 DA/428/2025 det. 22/01/2026 additional 10 storeys (60 apartments)

40. Prior to the issue of the Construction Certificate, the following must be demonstrated to the satisfaction of the Principal Certifying Authority: a) All opaque materials used on the facade must have a specular solar light reflectivity of no greater than 20%. b) All balcony glazing must have a visible light reflectivity value not greater than 8% (measured at the normal angle). c) All other glazing must have a visible light reflectivity not greater than 20% (measured at the normal angle). Reason: To deliver the solar reflectivity (glare) objectives of the DCP. Natural Ventilation

Condition 31 DA/545/2024 det. 17/12/2025 Carlingford Apartments

31. Service ducts, plumbing installations and plant servicing the development must be concealed within the building to keep external walls free from service installations. Downpipes may be located externally on balconies. Details are to be included within the plans and documentation accompanying the relevant Construction Certificate(s) to the satisfaction of the Principal Certifier. Reason: To ensure the quality built form of the development. Single master TV antenna