3. Synthetic turf that is located on areas nominated as deep soil is to be substituted with natural turf. Condition reason: To ensure that detailed landscaping requirements are documented. (21) Section 7.12 contributions - Before the issue of a construction certificate, contributions must be made to Council under section 7.12 of the Environmental Planning and Assessment Act 1979: Camden Section 7.12 Development Contribution Plan % of development 1% OF DEVELOPMENT COST cost Amount payable $62,941.00 The amount of contribution payable under this condition has been calculated at the date of determination. In accordance with the provisions of the contributions plan, this amount shall be indexed…
3. Amended plans are required to be submitted to the certifier that demonstrates that the proposed swimming pool will be constructed and include a swimming pool barrier which complies with the requirements of AS 1926.1-2012 – Swimming Pool Safety – Part 1: Safety barriers for swimming pools. Condition reason: To ensure that required information is provided to the certifier. (25) Section 7.12 contributions - Before the issue of a construction certificate, contributions must be made to Council under section 7.12 of the Environmental Planning and Assessment Act 1979: Page 13 OFFICIAL Camden Section 7.12 Development Contribution Plan % of 1% OF DEVELOPMENT COST development cost Amount payable…
2. The owner of the adjoining land gives written consent to the condition not applying. Condition reason: Prescribed condition under section 74 of the Environmental Planning and Assessment Regulation 2021. OFFICIAL (15) Salinity Management - The installation of services, infrastructure, and construction of the proposed development is to comply with the recommendations outlined in Salinity Assessment, Proposed Residential Development, Corner of South Circuit and Civic Way, Oran Park NSW, prepared by Douglas Partners, dated 24 February 2025, Project 230424.23. Condition reason: To ensure the development is designed to withstand the effects of salinity. (16) Mechanical Plant – The selection…
3. The landscape plan must be amended to provide a minimum of 9.5m3 of soil volume for feature trees located in the western outdoor play area. Condition reason: To ensure that detailed landscaping requirements are documented. (19) Section 7.12 contributions - Before the issue of a construction certificate, contributions must be made to Council under section 7.12 of the Environmental Planning and Assessment Act 1979: Camden Section 7.12 Development Contribution Plan % of development 1% OF DEVELOPMENT COST cost Amount payable $73,175 The amount of contribution payable under this condition has been calculated at the date of determination. In accordance with the provisions of the contributions…
2. No contributions or levies have been required since the document was issued. Page 22 DA/2025/414/1 OFFICIAL DA/2025/414/1 - Recommended Conditions of Consent – 62 Central Avenue, Oran Park Condition reason: To require evidence that a special infrastructure contribution has been paid if required. (12) Mechanical exhaust system – Before the issue of an occupation certificate, information must be prepared by a suitably qualified person and demonstrate, to the principal certifier’s satisfaction, that: