Bayside Developer Contributions Conditions

7 developer contributions conditions imposed by Bayside across 2 development applications in our dataset. Developer contribution conditions require monetary contributions toward public infrastructure and services under section 7.11 and 7.12 of the EP&A Act or a voluntary planning agreement.

Condition 2 DA-2024/205 det. 29/05/2025 Integrated Development - BATA 2 - Lot F

2. The amount payable at the time of payment is the amount shown in condition 1 as the total housing and productivity contribution adjusted by multiplying it by: highest PPI number consent PPI number where: highest PPI number is the highest PPI number for a quarter following the June quarter 2023 and up to and including the 2nd last quarter before the quarter in which the payment is made, and consent PPI number is the PPI number last used to adjust HPC rates when consent was granted, and June quarter 2023 and PPI have the meanings given in clause 22 (4) of the Environmental Planning and Assessment (Housing and Productivity Contribution) Order 2023. If the amount adjusted in accordance with…

Condition 5 DA-2024/205 det. 29/05/2025 Integrated Development - BATA 2 - Lot F

5. If the Minister administering the Environmental Planning and Assessment Act 1979 agrees, the HPC (apart from any transport project component) may be made, instead of as a monetary contribution, in the following ways: a) the dedication or provision of land for the purpose of regional infrastructure in the region in which the development will be carried out, b) the carrying out of works for the purpose of regional infrastructure in the region in which the HPC development will be carried out. If the HPC is made partly as a monetary contribution, the amount of the part payable is the amount of the part adjusted in accordance with condition 2 at the time of payment.

Condition 6 DA-2024/205 det. 29/05/2025 Integrated Development - BATA 2 - Lot F

6. Despite condition 1, a housing and productivity contribution is not required to be made to the extent that a planning agreement excludes the application of Subdivision 4 of Division 7.1 of the Environmental Planning and Assessment Act 1979 to the development, or the Environmental Planning and Assessment (Housing and Productivity Contribution) Order 2023 exempts the development from the contribution. The amount of the contribution may also be reduced under the order, including if payment is made before 1 July 2025. Bayside Council Page 32 of 87 DA-2024/169 REASON To comply with relevant legislation.

Condition 29 MDA-2025/27 det. 23/07/2025 Residential Aged Care Facility

29. Section 7.11 Contributions Deleted Notes: (a) Deleted in Land and Environment Court Proceedings No. 2022/00360916 in lieu of the entering into of the VPA. (b) See condition 9A inserted in Land and Environment Court Proceedings No. 2022/00360916; (c) See also clause 6.5 of the VPA, which deals with contributions under the VPA in the event that an application is made to modify this consent that changes the number of beds in the development. [Inserted in Land and Environment Court Proceedings No. 2022/00360916]

Condition 1 DA-2024/205 det. 29/05/2025 Integrated Development - BATA 2 - Lot F

1. The housing and productivity contribution (HPC) set out in the table below, but as adjusted in accordance with condition 2, is required to be made: Housing and Productivity Contribution Amount Housing and productivity contribution (base $2,399,186.31 component)

Condition 4 DA-2024/205 det. 29/05/2025 Integrated Development - BATA 2 - Lot F

4. The HPC must be paid using the NSW Planning Portal (https://pp.planningportal.nsw.gov.au/).

Condition 46 DA-2024/205 det. 29/05/2025 Integrated Development - BATA 2 - Lot F

46. Housing and Productivity Contribution

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.