Campbelltown Developer Contributions Conditions
18 developer contributions conditions imposed by Campbelltown across 3 development applications in our dataset. Developer contribution conditions require monetary contributions toward public infrastructure and services under section 7.11 and 7.12 of the EP&A Act or a voluntary planning agreement.
2. The amount payable at the time of payment is the amount shown in condition 1 as the total housing and productivity contribution adjusted by multiplying it by: πππππππ π·π·π° ππππππ πππππππ π·π·π° ππππππ where: highest PPI number is the highest PPI number for a quarter following the June quarter 2023 and up to and including the 2nd last quarter before the quarter in which the payment is made, and consent PPI number is the PPI number last used to adjust HPC rates when consent was granted, and June quarter 2023 and PPI have the meanings given in clause 22 (4) of the Environmental Planning and Assessment (Housing and Productivity Contribution) Order 2023. If theβ¦
2. The amount payable at the time of payment is the amount shown in part 1 as the total housing and productivity contribution adjusted by multiplying it by: πππππππ π·π·π° ππππππ πππππππ π·π·π° ππππππ where: highest PPI number is the highest PPI number for a quarter following the June quarter 2023 and up to and including the 2nd last quarter before the quarter in which the payment is made, and consent PPI number is the PPI number last used to adjust HPC rates when consent was granted, and June quarter 2023 and PPI have the meanings given in clause 22 (4) of the Environmental Planning and Assessment (Housing and Productivity Contribution) Order 2023. If the amountβ¦
2. The amount payable at the time of payment is the amount shown in condition 1 as the total housing and productivity contribution adjusted by multiplying it by: highest PPI number consent PPI number where: highest PPI number is the highest PPI number for a quarter following the June quarter 2023 and up to and including the 2nd last quarter before the quarter in which the payment is made, and consent PPI number is the PPI number last used to adjust HPC rates when consent was granted, and June quarter 2023 and PPI have the meanings given in clause 22 (4) of the Environmental Planning and Assessment (Housing and Productivity Contribution) Order 2023. If the amount adjusted in accordance withβ¦
5. If the Minister administering the Environmental Planning and Assessment Act 1979 agrees, the HPC (apart from any transport project component) may be made, instead of as a monetary contribution, in the following ways: a. the dedication or provision of land for the purpose of regional infrastructure in the region in which the development will be carried out, b. the carrying out of works for the purpose of regional infrastructure in the region in which the HPC development will be carried out. If the HPC is made partly as a monetary contribution, the amount of the part payable is the amount of the part adjusted in accordance with condition 2 at the time of payment.
5. If the Minister administering the Environmental Planning and Assessment Act 1979 agrees, the HPC (apart from any transport project component) may be made, instead of as a monetary contribution, in the following ways: a) the dedication or provision of land for the purpose of regional infrastructure in the region in which the development will be carried out, b) the carrying out of works for the purpose of regional infrastructure in the region in which the HPC development will be carried out. If the HPC is made partly as a monetary contribution, the amount of the part payable is the amount of the part adjusted in accordance with condition 2 at the time of payment.
5. If the Minister administering the Environmental Planning and Assessment Act 1979 agrees, the HPC (apart from any transport project component) may be made, instead of as a monetary contribution, in the following ways: a. the dedication or provision of land for the purpose of regional infrastructure in the region in which the development will be carried out, b. the carrying out of works for the purpose of regional infrastructure in the region in which the HPC development will be carried out. If the HPC is made partly as a monetary contribution, the amount of the part payable is the amount of the part adjusted in accordance with condition 2 at the time of payment.
6. Despite condition 1, a housing and productivity contribution is not required to be made to the extent that a planning agreement excludes the application of Subdivision 4 of Division 7.1 of the Environmental Planning and Assessment Act 1979 to the development, or the Environmental Planning and Assessment (Housing and Productivity Contribution) Order 2023 exempts the development from the contribution. The amount of the contribution may also be reduced under the order, including if payment is made before 1 July 2025. Condition reason: To contribute to the provision of public amenities and services to meet the increased demands created by the new development.
56. Payment of Section 7.11 Contributions Before the issue of a subdivision certificate, payment of Section 7.11 contributions applicable under the Campbelltown Local Infrastructure Plan 2018 must be made for the six allotments to be created under this consent, unless a Voluntary Planning Agreement has been executed or a draft letter of offer accepted in relation to the provision of infrastructure and/or contributions. Based on $20,000 per allotment, the applicable payment is $120,000. Condition reason: To contribute to the provision of public amenities and services to meet the increased demands created by the new development.
6. Despite condition 1, a housing and productivity contribution is not required to be made to the extent that a planning agreement excludes the application of Subdivision 4 of Division 7.1 of the Environmental Planning and Assessment Act 1979 to the development, or the Environmental Planning and Assessment (Housing and Productivity Contribution) Order 2023 exempts the development from the contribution. The amount of the contribution may also be reduced under the order, including if payment is made before 1 July 2025. Condition reason: To comply with state legislation.
1. The housing and productivity contribution (HPC) set out in the table below, but as adjusted in accordance with condition 2, is required to be made: Housing and productivity contribution Amount Housing and productivity contribution (base component) $90,822.25 Cumberland Plain Strategic Biodiversity Component HPC $72,128.49 Total housing and productivity contribution $162,950.74
1. The housing and productivity contribution (HPC) set out in the table below, but as adjusted in accordance with part 2, is required to be made: Housing and productivity contribution Amount Housing and productivity contribution (base $636,207.09 component) Transport project component $0.00 Total housing and productivity contribution $636,207.09
1. The housing and productivity contribution (HPC) set out in the table below, but as adjusted in accordance with condition 2, is required to be made: Housing and productivity contribution Amount Housing and productivity contribution (base $965,366.12 component) Transport project component Total housing and productivity contribution $965,366.12
4. The HPC must be paid using the NSW planning portal (https://pp.planningportal.nsw.gov.au/).
4. The HPC must be paid using the NSW planning portal (https://pp.planningportal.nsw.gov.au)
4. The HPC must be paid using the NSW planning portal (https://pp.planningportal.nsw.gov.au)
36. Housing and productivity contribution
56. Housing and productivity contribution
77. Housing and productivity contribution
Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.