9,484 conditions across 37 councils · 295 audit errors found across 33 councils · Newcastle, Central Coast, Wollongong added · CB & Lake Mac document checkers live · 37-council directory with LEP links · LEP clause reference + key timeframes ·

North Sydney Operational Noise Conditions

4 operational noise conditions imposed by North Sydney across 4 development applications in our dataset. Operational noise conditions limit noise from a development once it is in use — acoustic reports, plant and equipment noise limits, restricted hours of operation and mechanical ventilation noise.

DA258/2023 det. 15/05/2025

Appropriate provision must be incorporated into the design of car parking areas to allow for the installation of charging facilities for electric vehicles. Certification confirming that that electric vehicle charging points can be installed at a later time within the basement of the building as required by the Charging Facility for Electric Vehicles condition that electric vehicle charging facilities are capable of being installed in parking areas as required by this condition is to be provided to the Principal Certifier with the Final Occupation Certificate. All costs incurred in achieving compliance with this condition shall be borne by the developer. (Reason: To promote sustainability…

DA30/2025 det. 10/07/2025

C32. The use of all plant and equipment installed on the premises must not: a) Contribute an LAeq(15min) which will cause the total LAeq(15min) from all plant and equipment operating contemporaneously on the site or in the strata scheme or in the mixed strata schemes to exceed the RBL by more than 5dB when measured at the boundary of any affected receiver. The modifying factor adjustments in Fact Sheet C of the NSW Environment Protection Authority Noise Policy for Industry 2017 shall be applied. b) Cause “offensive noise” as defined in the Protection of the Environment Operations Act 1997. 118-124 BENELONG ROAD AND 72 GERARD STREET, CREMORNE DRAFT CONDITIONS OF CONSENT DA 30/25 (PPSSNH-612)…

350/24 det. 26/09/2025

Noise from Plant and Equipment C63 • The use of all plant and equipment installed on the premises must not: • Contribute an LAeq(15min) which will cause the total LAeq(15min) from all plant and equipment operating contemporaneously on the site or in the strata scheme or in the mixed strata schemes to exceed the RBL by more than 5dB when measured at the boundary of any affected receiver. The modifying factor adjustments in Fact Sheet C of the NSW Environment Protection Authority Noise Policy for Industry 2017 shall be applied. • Cause “offensive noise” as defined in the Protection of the Environment Operations Act 1997. “affected receiver” includes residential premises (including any lot in…

Condition 3 DA34/2025 det. 21/07/2025 Demolition and adaptive reuse

3. Apartment Noise Attenuation Design 1 Council is broadly satisfied that the design achieves the design intent of the ADG with respect to 4H of the ADG with - Acoustic measures is considered to be adequately addressed by both condition Nos. C36, C37, C38 & G23. However, it is also agreed that additional certification is reasonable and the Panel’s preferred Apartment Noise Attenuation Design condition has been added. Please Refer condition C38.