Canterbury-Bankstown Operational Noise Conditions

16 operational noise conditions imposed by Canterbury-Bankstown across 6 development applications in our dataset. Operational noise conditions limit noise from a development once it is in use — acoustic reports, plant and equipment noise limits, restricted hours of operation and mechanical ventilation noise.

Condition 6 DA-914/2024 det. 12/03/2025 Canterbury Olympic Ice Rink

6. Conditions of Use 6.1 Plan of Management The premises are to be managed in accordance with the Approved Plan of Management referenced in this consent and as amended in accordance with conditions of this consent. Any future changes to the Approved Plan of Management must be submitted to and approved by Canterbury-Bankstown Council’s Manager Development. Condition reason: To comply with the requirements of this consent. 6.2 Fire Safety During occupation and ongoing use of the building, the consent holder must provide an annual fire safety statement to Council and the Commissioner of Fire and Rescue NSW in accordance with clause 177 of the EP&A Regulation. Condition reason: To ensure…

Condition 109 DA-1182/2024 det. 13/02/2026 Compass Centre

109. Comply with Waste management plan The requirements of the submitted Waste Management Plan shall be complied with at all times that work is being carried out. Without limiting the foregoing, compliance shall include the following: a. The disposal of any demolition and construction waste must be undertaken in accordance with the requirements of the Protection of Environment Operations Act 1997; and b. All waste on site is to be stored, handled and disposed of in such a manner as to not create air pollution, offensive noise or pollution of land and water as defined by the Protection of Environment Operations Act 1997; and c. Generation, storage, treatment and disposal of hazardous waste…

DA-1049/2024 det. 15/04/2025

Comply with Waste management plan The requirements of the submitted Waste Management Plan shall be complied with at all times that work is being carried out. Without limiting the foregoing, compliance shall include the following: The disposal of any demolition and construction waste must be undertaken in accordance with the requirements of the Protection of Environment Operations Act 1997; and All waste on site is to be stored, handled and disposed of in such a manner as to not create air pollution, offensive noise or pollution of land and water as defined by the Protection of Environment Operations Act 1997; and Generation, storage, treatment and disposal of hazardous waste is conducted in…

DA-2/2025 det. 08/09/2025

Comply with Waste management plan The requirements of the submitted Waste Management Plan shall be complied with at all times that work is being carried out. Without limiting the foregoing, compliance shall include the following: The disposal of any demolition and construction waste must be undertaken in accordance with the requirements of the Protection of Environment Operations Act 1997; and All waste on site is to be stored, handled and disposed of in such a manner as to not create air pollution, offensive noise or pollution of land and water as defined by the Protection of Environment Operations Act 1997; and Generation, storage, treatment and disposal of hazardous waste is conducted in…

DA-289/2025 det. 26/08/2025

Comply with Waste management plan The requirements of the submitted Waste Management Plan shall be complied with at all times that work is being carried out. Without limiting the foregoing, compliance shall include the following: The disposal of any demolition and construction waste must be undertaken in accordance with the requirements of the Protection of Environment Operations Act 1997; and All waste on site is to be stored, handled and disposed of in such a manner as to not create air pollution, offensive noise or pollution of land and water as defined by the Protection of Environment Operations Act 1997; and Generation, storage, treatment and disposal of hazardous waste is conducted in…

DA-811/2025 det. 08/12/2025

• Validation of the remedial action; • Summary of feedback to the complainant and name of employee who gave the feedback. Incident includes: • Any breach of a plan of management (where applicable); • Any complaint by any person about the operation of the premises; • Any complaint by any person about noise emanating from the premises; or • Any event that may cause concern to any person as a result of the conduct and/or an act of any person(s) on, entering or exiting the premises. All complaints shall have an initial investigation commence within seven (7) days from the date of receipt of complaint. The Complaints Register must always be held on the premises and shall be reviewed monthly by…

Condition 190 DA-1182/2024 det. 13/02/2026 Compass Centre

190. Waste Storage and Disposal – Multistorey Premises The waste storage room must be provided with smooth and impervious walls and floors and coved at the intersection of the floor and walls. Floor areas must be graded and drained to a floor waste gully connected to the sewer. Waste storage rooms must be well ventilated and proofed against pests. The area or room must be provided with water service hose connectors to enable easy cleaning. Open waste storage areas must be appropriately covered and bunded. The ground must be paved with impervious material and must be graded and drained to a wastewater disposal system according to Sydney Water’s requirements. A hose tap connected to a water…

Condition 3 DA-1182/2024 det. 13/02/2026 Compass Centre

3. Before the issue of the relevant construction certificate, the certifier must ensure the approved construction certificate plans (and specifications) detail the following required design amendments to the approved plans (stamped by Council) and supporting documentation. The design amendments listed below are to be reflected on updated plans and submitted and approved by Council: a. The private open space areas of Units C201 and C203 shall be extended to allow for the balcony of C201 to wrap around its eastern edge and for the balcony of C203 to wrap around its western edge. These wrap around elements should have a minimum dimension of 5 metres in a north-south direction. b. Improved…

Condition 176 DA-1182/2024 det. 13/02/2026 Compass Centre

176. Further Acoustic Assessment Following occupation of the building/premises, should it be found that the measures recommended in the acoustic assessment are not sufficient, or have been incorrectly installed or a noise issue (relating to the development) not previously identified arises (through complaint or otherwise), the owner/ occupier must, upon request by Council, employ the services of a qualified acoustic consultant who has not previously been involved with the development to undertake a post-occupation assessment of the development and complete an acoustic report with recommendations to rectify the situation. A copy of this acoustic assessment report must be submitted to Council…

Condition 162 DA-1182/2024 det. 13/02/2026 Compass Centre

162. Acoustic Report The acoustic report prepared by E-Lab Consulting Pty Ltd, titled Barings Compass Centre Bankstown, reference number P00709 dated 7 November 2025 and all the recommendations stated within the report, form part of the development consent. The principal certifier shall obtain a report from an appropriately qualified acoustic consultant, not previously involved with the development, stating that the recommendations outlined in the above-mentioned acoustic report have been implemented and that the relevant noise criteria have been satisfied prior to the issue of any occupation certificate. A copy of the report is to be submitted to Council prior to the issue of an occupation…

Condition 185 DA-1182/2024 det. 13/02/2026 Compass Centre

185. Waste generated on site All waste generated on the site is to be stored, handled and disposed of in such a manner as to not create offensive odour, offensive noise or pollution of land and/or water as defined under the Protection of the Environment Operations Act 1997. All waste generated shall be removed and disposed of by an authorised waste removal contractor. A copy of the waste removal agreement and receipts shall be made available to Council on request. Condition reason: To protect and enhance the amenity of the occupants of the development site and the occupants of adjoining sites.

Condition 93 DA-1182/2024 det. 13/02/2026 Compass Centre

93. Pool filter noise The use of the pool / spa filter equipment must not give rise to offensive noise as defined in the Protection of the Environment Operations Act 1997 and Protection of the Environment Operations (Noise Control) Regulation 2000. All noise emitting equipment must be housed in an insulated enclosure or appropriately positioned so as to cause no nuisance to neighbours. Condition reason: To protect and enhance the amenity of the occupants of the development site and the occupants of adjoining sites.

Condition 172 DA-1182/2024 det. 13/02/2026 Compass Centre

172. Hotel external areas The following maximum capacities within the Hotel external areas shall be complied with at all times in accordance with the acoustic report prepared by E-Lab Consulting Pty Ltd, titled Barings Compass Centre Bankstown, reference number P00709 dated 7 November 2025: • 7 people within the bar balcony on Level 5 • 28 people within the rooftop bar • 35 people within the external terrace adjacent to the hotel ballroom on Level 4 Condition reason: To protect the amenity of the surrounding area.

Condition 199 DA-1182/2024 det. 13/02/2026 Compass Centre

199. Protection of the Environment Operations Act 1997 – General Any activity carried out in accordance with this approval must not give rise to offensive odour, offensive noise or pollution of air, land or water as defined in the Protection of the Environment Operations Act 1997 and Regulations. Condition reason: To ensure compliance with the relevant New South Wales legislation.

Condition 178 DA-1182/2024 det. 13/02/2026 Compass Centre

178. Vibration The use of the premises and the operation of plant and equipment must not give rise to the transmission of a vibration nuisance or damage to other premises as defined in the ‘Assessing Vibration: A Technical Guideline’ (NSW Department of Environment and Conservation, 2006). Condition reason: To protect the amenity of the surrounding area.

Condition 177 DA-1182/2024 det. 13/02/2026 Compass Centre

177. Compliance with Noise Control Legislation The applicant must ensure that all activities within the premises comply with the relevant sections of the Protection of the Environment Operations Act 1997 and Regulations and the Noise Policy for Industry (NSW EPA, 2017). Condition reason: To protect the amenity of the surrounding area.

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.