9,484 conditions across 37 councils · 295 audit errors found across 33 councils · Newcastle, Central Coast, Wollongong added · CB & Lake Mac document checkers live · 37-council directory with LEP links · LEP clause reference + key timeframes ·

Georges River BASIX Compliance Conditions

4 basix compliance conditions imposed by Georges River across 2 development applications in our dataset. BASIX conditions require residential development to meet NSW targets for water use, thermal comfort and energy efficiency, with the commitments on the BASIX certificate shown on plans and certified at completion.

Condition 53 DA2021/0306 Demolition works and construction of residential flat building

53. BASIX Compliance Certificate - A Compliance Certificate must be provided to the Crown Certifier regarding the implementation of all energy efficiency measures as detailed in the approved BASIX Certificate before Occupation.

Condition 56 DA2024/0612 det. 08/09/2025 Affordable Housing Residential Flat Building

56. BASIX Compliance Certificate A Compliance Certificate must be provided to the Crown Certifier regarding the implementation of all energy efficiency measures as detailed in the approved BASIX Certificate before occupation.

Condition 19 DA2021/0306 Demolition works and construction of residential flat building

19. BASIX Commitments - All energy efficiency measures as detailed in the BASIX Certificate No. 1181907M dated 25 May 2021 must be implemented on the plans lodged with the Crown Certifier.

Condition 55 DA2024/0612 det. 08/09/2025 Affordable Housing Residential Flat Building

55. BASIX Commitments - All energy efficiency measures as detailed in the approved BASIX Certificate No. BSX-27882M_02 dated 29 October 2024 must be implemented before occupation.

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.