9,484 conditions across 37 councils · 295 audit errors found across 33 councils · Newcastle, Central Coast, Wollongong added · CB & Lake Mac document checkers live · 37-council directory with LEP links · LEP clause reference + key timeframes ·

Canterbury-Bankstown Demolition Conditions

21 demolition conditions imposed by Canterbury-Bankstown across 4 development applications in our dataset. Demolition conditions set requirements for safely removing existing structures — demolition work plans, asbestos removal and disposal, waste classification, hoarding, and notification of neighbours and authorities.

Condition 5 DA-1182/2024 det. 13/02/2026 Compass Centre

5. Demolition The demolition of all structures on the property must be undertaken in accordance with all the following: a. Written notice must be issued to adjoining residents a minimum of seven (7) days before the commencement of demolition advising of the commencement date, b. Written notice must be issued to Council for inspection a minimum of (7) days before the commencement of demolition. Written notice must include the date when demolition work will commence and details of the name, address, contact telephone number and licence number of the demolition contractor, c. Inspections being undertaken by Council including: i. A pre-commencement demolition inspection when all site works…

DA-289/2025 det. 26/08/2025

GT0241-00001 A construction certificate can be issued for excavation work in accordance with a valid development consent, however dewatering cannot take place without an Approval being granted by Water NSW for any water supply works required by the development. If the excavation work will or is likely to require dewatering, the applicant must apply and obtain, an approval under the Water Management Act 2000 prior to any dewatering taking place and notify WaterNSW of the programme for the dewatering activity including the commencement and proposed completion dates of the dewatering activity. Advisory Note: An approval under the Water Management Act 2000 is required to construct and/or…

DA-2/2025 det. 08/09/2025

The demolition must be undertaken in accordance with all the following: Written notice must be issued to adjoining residents a minimum of seven (7) days before the commencement of demolition advising of the commencement date, Written notice must be issued to Council for inspection a minimum of (7) days before the commencement of demolition. Written notice must include the date when demolition work will commence and details of the name, address, contact telephone number and licence number of the demolition contractor, Inspections being undertaken by Council including: A pre-commencement demolition inspection when all site works required as part of this Determination Notice are installed on…

Condition 1 DA-1524/2023

1. Amend Condition 27 to remove the paragraph commencing with words “If the engineer is denied access ….” to read as follows: Dilapidation report Before the issue of a construction certificate, a suitably qualified engineer must prepare a dilapidation report detailing the structural condition of adjoining buildings, structures or works, and public land, to the satisfaction of the certifier. The adjoining buildings include the following properties: • Southern adjoining properties: 83 – 85 Auburn Road, Birrong • Eastern adjoining property: 15 Neutral Avenue, Birrong. Where access has not been granted to any adjoining properties to prepare the dilapidation report, the report must be based on a…

Condition 22 DA-1182/2024 det. 13/02/2026 Compass Centre

22. Dilapidation report Before the issue of the first construction certificate, a dilapidation report must be prepared by a suitably qualified engineer detailing the structural condition of adjoining buildings, structures or works and public land, to the satisfaction of the certifier for the following properties: • 3-7 Fetherstone Street • 62 The Mall Where access has not been granted to any adjoining properties to prepare the dilapidation report, the report must be based on a survey of what can be observed externally and demonstrate, in writing, to the satisfaction of the certifier, that all reasonable steps were taken to obtain access to the adjoining properties. No less than 14 days…

Condition 137 DA-1182/2024 det. 13/02/2026 Compass Centre

137. Post-construction dilapidation report Before the issue of an occupation certificate, a post-construction dilapidation report must prepared by a suitably qualified engineer, to the satisfaction of the principal certifier, detailing whether: a. after comparing the pre-construction dilapidation report to the post- construction dilapidation report required under this condition, there has been any structural damage to any adjoining buildings; and b. where there has been structural damage to any adjoining buildings, that it is a result of the work approved under this development consent, and c. a copy of the post-construction dilapidation report must be provided to council (where council is…

Condition 91 DA-1182/2024 det. 13/02/2026 Compass Centre

91. Adjacent to Council Pipe Development located adjacent to Council’s drainage pipe and/or easements shall comply with the following: a. Concrete Pier and beam type footings/foundations adjacent to Council’s drainage easements shall be constructed in accordance with the approved details and Council’s Development Engineering Standards. The consent holder/developer shall arrange for an inspection to be carried out by Council to verify depth and location of piers in relation to the pipe and easement before pouring of concrete. b. Any disturbance or damage caused to Council’s drainage pipes within the site shall be repaired by Council at the consent holder’s expense. The consent holder shall…

Condition 15 DA-1182/2024 det. 13/02/2026 Compass Centre

15. Submit Plans to Sydney Water DA-1182/2024 10 The Council approved plans, including demolition plans, must be submitted to Sydney Water for assessment prior to the first construction certificate. This will determine if the proposed structure(s) will affect any Sydney Water infrastructure or if there are additional requirements. Building plan approvals can be submitted online via Sydney Water TAP INTM. Refer to www.sydneywater.com.au/tapin for Sydney Water’s Guidelines for building over or next to assets, visit www.sydneywater.com.au ‘Plumbing, building & developing’ then ‘Building Plan Approvals’ or call 13000 TAP INTM. Sydney Water must issue either a Building Plan Assessment letter…

Condition 81 DA-1182/2024 det. 13/02/2026 Compass Centre

81. A sign must be erected in a prominent position on any site on which building work or demolition work is being carried out: a. Showing the name, address and telephone number of the principal certifier for the work, and b. Showing the name of the principal contractor (if any) for any building work and a telephone number on which that person may be contacted outside working hours, and c. Stating that unauthorised entry to the work site is prohibited. Any such sign is to be maintained while the building work and demolition work is being carried out and must be removed when the work has been completed. Note: This does not apply in relation to building work or demolition work that is carried…

Condition 146 DA-1182/2024 det. 13/02/2026 Compass Centre

146. Repair of infrastructure Before the issue of an occupation certificate: a. any public infrastructure damaged as a result of the carrying out of work approved under this consent (including damage caused by, but not limited to, delivery vehicles, waste collection, contractors, sub- contractors, concreting vehicles) must be fully repaired to the written satisfaction of council, and at no cost to council, or b. if the works in (a) are not carried out to council’s satisfaction, council may carry out the works required and the costs of any such works must be paid as directed by council and in the first instance will be paid using the security deposit required to be paid under this consent.…

Condition 75 DA-1182/2024 det. 13/02/2026 Compass Centre

75. Section 73 Compliance Certificate A Section 73 Compliance Certificate under the Sydney Water Act 1994 must be obtained from Sydney Water. It is recommended that the consent holder apply early for the certificate, as there may be water and sewer pipes to be built and this can take some time. This can also impact on other services and building, driveway or landscape design. Application can be made through an authorised Water Servicing Coordinator. For help either visit www.sydneywater.com.au > Plumbing, building and developing > Developing > Section 73 Compliance Certificates, or telephone 13 20 92. Condition reason: To protect existing public and private infrastructure and building works…

Condition 89 DA-1182/2024 det. 13/02/2026 Compass Centre

89. Noise and Vibration While site work is being carried out, noise generated from the site must be controlled in accordance with the requirements of the approved documentation. Where no noise and vibration management plan is approved under this consent, the certifier is to ensure that any noise caused by demolition, vegetation removal or construction does not exceed an LAeq (15 min) of 5dB(A) above background noise, when measured at any lot boundary of the property where the site work is being carried out. DA-1182/2024 34 Condition reason: To protect and enhance the amenity of the occupants of the development site and the occupants of adjoining sites.

Condition 136 DA-1182/2024 det. 13/02/2026 Compass Centre

136. Preservation of survey marks Before the issue of an occupation certificate, a registered surveyor must submit documentation to the principal certifier which demonstrates that: a. no existing survey mark(s) have been removed, damaged, destroyed, obliterated or defaced, or b. any survey mark(s) that were damaged, destroyed, obliterated or defaced have been re-established in accordance with the Surveyor General’s Direction No. 11 – Preservation of Survey Infrastructure. Condition reason: To protect existing public and private infrastructure and building works during demolition, construction and ongoing use of the development.

Condition 139 DA-1182/2024 det. 13/02/2026 Compass Centre

139. Completion of Public Utility Services Before the issue of the relevant occupation certificate, confirmation must be obtained from the relevant authority that any adjustment or augmentation of any public utility services including gas, water, sewer, electricity, street lighting and telecommunications, required as a result of the development, have been completed and this confirmation must be provided to the principal certifier. Condition reason: To protect existing public and private infrastructure and building works during demolition, construction and ongoing use of the development.

Condition 6 DA-1182/2024 det. 13/02/2026 Compass Centre

6. Demolition Waste All waste material generated during demolition must be disposed of at an appropriately licensed waste facility for the specific waste. All waste must be transported by a contractor licensed to transport the specific waste, and in vehicles capable of carting the waste without spillage and meeting relevant requirements and standards. All loads must be covered prior to vehicles leaving the site. Condition reason: To ensure compliance with the relevant New South Wales legislation. BUILDING WORK BEFORE ISSUE OF A CONSTRUCTION CERTIFICATE

Condition 77 DA-1182/2024 det. 13/02/2026 Compass Centre

77. Dilapidation report Before the commencement of any site or building work, the principal certifier must ensure the adjoining building owner(s) is provided with a copy of the dilapidation report for their property(ies) no less than 7 (seven) days before the commencement of any site or building works and provide a copy of the report to Council at the same time. Condition reason: To protect existing public and private infrastructure and building works during demolition, construction and ongoing use of the development.

Condition 110 DA-1182/2024 det. 13/02/2026 Compass Centre

110. Construction and Demolition Waste All waste material generated during construction must be disposed of at an appropriately licensed waste facility for the specific waste. All waste must be transported by a contractor licensed to transport the specific waste, and in vehicles capable of carting the waste without spillage and meeting relevant requirements and standards. All loads must be covered prior to vehicles leaving the site. Condition reason: To ensure compliance with the relevant New South Wales legislation.

Condition 25 DA-1182/2024 det. 13/02/2026 Compass Centre

25. Basement Anchoring The basement of the development is located adjacent to a Council public road reserve. Separate approval and Work Permit is to be obtained from Council for any temporary or permanent anchoring works under Council's public road, prior to the issue of a relevant construction certificate. Condition reason: To protect existing public and private infrastructure and building works during demolition, construction and ongoing use of the development.

Condition 80 DA-1182/2024 det. 13/02/2026 Compass Centre

80. Soil and water management warning sign Council’s warning sign for Soil and Water Management must be displayed throughout the construction period at the most prominent point of the site, visible to both the street and site. Condition reason: To protect existing public and private infrastructure and building works during demolition, construction and ongoing use of the development. Sign with principal certifier details DA-1182/2024 32

Condition 88 DA-1182/2024 det. 13/02/2026 Compass Centre

88. Hours of Work Building work or demolition work may only be carried out between 7.00 am and 6.00 pm on Monday to Friday, or between 8.00 am and 1.00 pm on Saturdays, and no construction is to be carried out at any time on a Sunday or a public holiday. Condition reason: To protect and enhance the amenity of the occupants of the development site and the occupants of adjoining sites.

Condition 114 DA-1182/2024 det. 13/02/2026 Compass Centre

114. Car wash bunding The carwash bay is to be bunded and connected to the sewer system to dispose of wastewater in accordance with the requirements contained in Council's Development Engineering Standards. Condition reason: To protect existing public and private infrastructure and building works during demolition, construction and ongoing use of the development.

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.