9,484 conditions across 37 councils · 295 audit errors found across 33 councils · Newcastle, Central Coast, Wollongong added · CB & Lake Mac document checkers live · 37-council directory with LEP links · LEP clause reference + key timeframes ·

Biodiversity Conditions

Biodiversity conditions protect native vegetation and habitat — biodiversity offsets, landscaping with locally native species, fauna management and protection of threatened species and ecological communities.

513

Conditions

36

Councils

156

DAs

Example biodiversity conditions

Bayside DA-2024/293 2 x 10 storey residential flat buildings

3. The waste generated on site during construction must be classified in accordance with the Environment Protection Authority’s Waste Classification Guidelines, 2014 (as amended from time to time) and disposed of to an approved waste management facility or otherwise lawfully managed. If waste has been removed from the site where the waste is under an Environment Protection Authority Resource Recovery Order or Exemption, records in relation to and required by that Order or…

Canada Bay DA2024/0064 Residential Apartment Building

1. Commitments for Residential flat buildings - Building A (a) Dwellings (i) Water Show on Show on CC/CDC Certifier DA plans plans & specs check (a) The applicant must comply with the commitments listed below in carrying out the development of a dwelling listed in a table below. (b) The applicant must plant indigenous or low water use species of vegetation throughout the area of land specified for the dwelling in the "Indigenous species" column of the table below, as private…

Georges River DA2024/0612 Affordable Housing Residential Flat Building

83. On-going Operational Waste Management (a) The applicant must allow bin storage at the following ratios: i. 120L general waste per unit per week – equivalent to: 21 x 240L general waste bins per week, serviced once weekly, OR 8 x 660L general waste bins per week, serviced once weekly, OR 5 x 1,100L general waste bins per week, serviced once weekly, Ref: DA2024/0612 Page 43 of 52 ii. 120L recycling per unit per week – equivalent to: 21 x 240L general waste bins per week,…

Willoughby DA-2024/159 Residential Flat Buildings

2. Ausgrid Ausgrid consents to the above mentioned development subject to the following conditions:- A Method of Electricity Connection The method of connection will be in line with Ausgrid’s Electrical Standard (ES)1 – ‘Premise Connection Requirements. B Supply of Electricity It is recommended for the nominated electrical consultant/contractor to provide a preliminary enquiry to Ausgrid to obtain advice for the connection of the proposed development to the adjacent…

Hornsby DA/1024/2021/B 4.55(2) Modification - Seniors housing development

89. Electrolysis Prior to the issue of a Construction Certificate, the Applicant must incorporate in the development all the measures recommended in the Electrolysis Risk Report (CCE Ref: W21460/NSW-P000675, Revision 0) prepared by Corrosion Control Engineering dated 5 November 2021. A copy of the electrolysis report is to be provided to the Certifier with the application for a Construction Certificate. Prior to issuing a Construction Certificate for the development, the…

Lane Cove 35/2024 Demolition & construction of residential flat building

7. A.7.L Tree preservation and approved landscaping works The protection of trees in Lane Cove is regulated under the State Environmental Planning Policy (Biodiversity and Conservation) 2021 (SEPP) parts 2.2 and 2.3 which prohibits the clearing of vegetation without the authority conferred by a permit granted by Council. Clearing under the SEPP is defined as: (a) cut down, fell, uproot, kill, poison, ringbark, burn or otherwise destroy the vegetation, or (b) lop or otherwise…

City of Sydney D/2015/1414/B

2. Appropriate conditions of consent have been imposed to ensure that the development will not result in detrimental environmental impacts. Community Consultation As a Section 4.55(1A) modification, the application was not notified as by way of scale, character and operation the proposal is likely to have minimal or acceptable impacts. Right of Appeal If you are dissatisfied with this decision, Section 8.9 of the Environmental Planning and Assessment Act 1979 gives you the…

Wollongong DA-2023/895 Former Bulli Hospital

14. Housing and Productivity Contribution Below applies to applications ‘accepted’ between 01 Oct 2023 and 01 Jul 2024: a) The Housing and Productivity Contribution (HPC) set out in the table below, but as adjusted in accordance with condition b), is required to be made: Housing and Productivity Contribution Amount Housing and Productivity Contribution (base component) $8,145.03 Total Housing and Productivity Contribution $8,145.03 b) The amount payable at the time of…

Randwick DA/489/2024

5. Housing and productivity Contribution a) The housing and productivity contribution (HPC) set out in the table below, but as adjusted in accordance with condition 2, is required to be made: Housing and productivity Amount contribution Housing and productivity $40,000 3 Condition contribution (base component $10,000 x 4 units) Total housing and productivity $40,000 contribution b) The amount payable at the time of payment is the amount shown in condition a) as the total…

Strathfield DA2022.179 Warehouse / Distribution Centre - 41 Roberts Rd, Greenacre

24. Compliance with Submitted Arborist Report The recommendations outlined in the Arborist’s Report titled Arboricultural Impact Assessment dated 31 August 2022 prepared by CIVICA must be implemented throughout the relevant stages of construction. Details of tree protection measures to be implemented must be detailed and lodged with the Construction Certificate application for approval and shall be in accordance with Section 4 - Australian Standard AS 4970-2009: Protection…

Snippets shown for reference. Always verify against the original consent on the NSW Planning Portal.