9,484 conditions across 37 councils · 295 audit errors found across 33 councils · Newcastle, Central Coast, Wollongong added · CB & Lake Mac document checkers live · 37-council directory with LEP links · LEP clause reference + key timeframes ·

Northern Beaches Contamination Conditions

5 contamination conditions imposed by Northern Beaches across 3 development applications in our dataset. Contamination conditions manage land affected by past industrial, commercial or agricultural use — site investigation, remediation action plans, validation reporting and the safe handling of asbestos and hazardous material.

Condition 16 Mod2025/0381 det. 17/11/2025 S4.56 Modification to DA2015/0901

16. Add the following condition: 20D. Construction Traffic Management Plan (Stage 2 - Hotel/Motel) A Construction Traffic Management Plan (CTMP) and report shall be prepared by a Transport for NSW accredited person and submitted to Council via an application for a Permit to Implement Traffic Control. The application form can be accessed via https://www.northernbeaches.nsw.gov.au/council/forms. Approval of the permit application by the Northern Beaches Council Traffic Team is required prior to issue of any Construction Certificate. The CTMP must address following: The proposed phases of construction works on the site, and the expected duration of each construction phase. The proposed order…

DA2024/1303 det. 05/08/2025

A Dilapidation report, including photographic surveys, of the private road/driveway/right of way must be included prior to any works commencing on the site. The report must detail the physical condition of the private road/driveway/right of way, and any other adjacent private property assets (including trees) or adjacent public property that may be adversely affected by vehicles servicing the development site to undertake works or activity during site works. A requirement for Post-Construction Dilapidation Reports, including photos of any damage evident at the time of inspection, to be submitted after the completion of works and prior to the relevant Occupation certificate. The report must:…

Mod2024/0549 det. 03/02/2025

During demolition and/or construction the proposal/works shall be generally consistent with the Waste MOD2024/0549 Page 3 of 4 Management Plan submitted on 14/11/2022 as part of DA2022/1910. Reason: To ensure waste is minimised and adequate and appropriate waste and recycling facilities are provided. H. Add Condition 49A . Requirement to notify about new Acid Sulfate Soils evidence - to read as follows: Any new information revealed during excavation works that has the potential to alter previous conclusions about Acid Sulfate Soils shall be immediately notified to the Council and the Principal Certifier and a report be obtained from a suitably qualified person. Any recommendations provided…

Condition 34 Mod2025/0381 det. 17/11/2025 S4.56 Modification to DA2015/0901

34. Add the following condition: 24F. Construction Water Discharge (Stage 2 - Hotel/Motel) Any water to be discharged must be compliant with the Landcom’s ‘Managing Urban Stormwater: Soils and Construction’ (2004) (Blue Book), Council’s Compliance and Enforcement Policy and legislation including Protection of the Environment Operations Act 1997 and Contaminated Land Management Act 1997. All approvals, water discharges and monitoring results are to be documented and kept on site. Copies of all records shall be provided to the appropriate regulatory authority, including Council, upon request. Reason: Protection of the receiving environment.

Condition 26 Mod2025/0381 det. 17/11/2025 S4.56 Modification to DA2015/0901

26. Add the following condition: 24C. Requirement to know about new Contamination Evidence (Stage 2 - Hotel/Motel) Any new information revealed during demolition works that has the potential to alter previous conclusions about site contamination or hazardous materials shall be immediately notified to the Council and the Principal Certifier. Reason: To protect human health and the environment.

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.