9,484 conditions across 37 councils · 295 audit errors found across 33 councils · Newcastle, Central Coast, Wollongong added · CB & Lake Mac document checkers live · 37-council directory with LEP links · LEP clause reference + key timeframes ·

Willoughby Demolition Conditions

41 demolition conditions imposed by Willoughby across 5 development applications in our dataset. Demolition conditions set requirements for safely removing existing structures — demolition work plans, asbestos removal and disposal, waste classification, hoarding, and notification of neighbours and authorities.

Condition 63 DA-2024/106 det. 24/07/2025 Shop Top Housing

63. Noise and vibration management plan Prior to the commencement of any works, a noise and vibration management plan is to be prepared by a suitably qualified expert addressing the likely noise and Reference: DA-2024/106 Page 35 of 78 vibration from demolition, excavation and construction of the proposed development and provided to the Principal Certifier. The management plan is to identify amelioration measures to achieve the best practice objectives of Australian Standard 2436-2010 - Guide to noise and vibration control on construction, demolition and maintenance sites and NSW Department of Environment and Climate Change Interim Construction Noise Guidelines. The report shall be prepared…

Condition 73 DA-2023/256 det. 01/08/2025 Development Application

73. Hours of Work All construction/demolition work relating to this Development Consent within the City, unless varied by an Out of Hours Work Permit, must be carried out only between the hours of 7 am to 5 pm Mondays to Fridays and 7 am to 12 noon on Saturdays. No work is permitted on Sundays or Public Holidays. An application for an Out of Hours Work Permit to allow variation to these approved hours must be lodged with Council at least 48 hours prior to the proposed commencement of the work. The application must include a statement regarding the reasons for the variation sought, the type of work/s to be carried out, the additional Reference: DA-2023/256 Page 34 of 59 PPSSNH-433 time…

Condition 67 DA-2024/106 det. 24/07/2025 Shop Top Housing

67. Hours of Work All construction/demolition work relating to this Development Consent within the City, unless varied by an Out of Hours Work Permit, must be carried out only between the hours of 7 am to 5 pm Mondays to Fridays and 7 am to 12 noon on Saturdays. No work is permitted on Sundays or Public Holidays. Reference: DA-2024/106 Page 37 of 78 An application for an Out of Hours Work Permit to allow variation to these approved hours must be lodged with Council at least 48 hours prior to the proposed commencement of the work. The application must include a statement regarding the reasons for the variation sought, the type of work/s to be carried out, the additional time required, the…

Condition 70 DA-2024/13 det. 03/12/2024 Mixed Use Development

70. Hours of Work All construction/demolition work relating to this Development Consent within the City, unless varied by an Out of Hours Work Permit, must be carried out only between the hours of 7 am to 5 pm Mondays to Fridays and 7 am to 12 noon on Saturdays. No work is permitted on Sundays or Public Holidays. An application for an Out of Hours Work Permit to allow variation to these approved hours must be lodged with Council at least 48 hours prior to the proposed commencement of the work. The application must include a statement regarding the reasons for the variation sought, the type of work/s to be carried out, the additional time required, the anticipated impact upon the local…

Condition 70 DA-2023/334 det. 30/05/2025 Registered club and independent living units

70. Hours of Work All construction/demolition work relating to this Development Consent within the City, unless varied by an Out of Hours Work Permit, must be carried out only between the hours of 7 am to 5 pm Mondays to Fridays and 7 am to 12 noon on Saturdays. No work is permitted on Sundays or Public Holidays. An application for an Out of Hours Work Permit to allow variation to these approved hours must be lodged with Council at least 48 hours prior to the proposed commencement of the work. The application must include a statement regarding the reasons for the variation sought, the type of work/s to be carried out, the additional time required, the anticipated impact upon the local…

Condition 41 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

41. Hours of Work All construction/demolition work relating to this Development Consent within the City, unless varied by an Out of Hours Work Permit, must be carried out only between the hours of 7 am to 5 pm Mondays to Fridays and 7 am to 12 noon on Saturdays. No work is permitted on Sundays or Public Holidays. An application for an Out of Hours Work Permit to allow variation to these approved hours must be lodged with Council at least 48 hours prior to the proposed commencement of the work. The application must include a statement regarding the reasons for the variation sought, the type of work/s to be carried out, the additional time required, the anticipated impact upon the local…

Condition 6 DA-2023/256 det. 01/08/2025 Development Application

6. Sydney Airport Construction cranes may be required to operate at a height significantly higher than that of the proposed development and consequently, may not be approved under the Airports (Protection of Airspace) Regulations. a) Pursuant to s. 183 of the Airports Act 1996 and Reg 7 of the Airports (Protection of Airspace) Regulations 1996, the Proponent must apply through the Airport to the Secretary of the Department of Infrastructure and Regional Development for approval of the operation ("controlled activity") set out in the Schedule. Reference: DA-2023/256 Page 9 of 59 PPSSNH-433 b) An Application for approval must be given to the Airport at least 28 days before commencement of the…

Condition 6 DA-2023/256 det. 01/08/2025 Development Application

6. Sydney Airport Construction cranes may be required to operate at a height significantly higher than that of the proposed development and consequently, may not be approved under the Airports (Protection of Airspace) Regulations. a) Pursuant to s. 183 of the Airports Act 1996 and Reg 7 of the Airports (Protection of Airspace) Regulations 1996, the Proponent must apply through the Airport to the Secretary of the Department of Infrastructure and Regional Development for approval of the operation ("controlled activity") set out in the Schedule. b) An Application for approval must be given to the Airport at least 28 days before commencement of the operation. c) The operation must not commence…

Condition 66 DA-2024/106 det. 24/07/2025 Shop Top Housing

66. Dilapidation Report of Adjoining Properties Prior to commencement of work, submit a photographic survey and report of the adjoining properties 128 Sailors Bay Road Northbridge, 134 Sailors Bay Road Northbridge and 31 Baringa Road Northbridge to the Certifier and all owners of these adjoining properties. Such photographic survey and report shall be prepared by a suitably qualified person, detailing the physical condition of these properties, both internal and external including items as walls, ceilings, roof, structural members and other items as necessary. In the event of a property owner refusing to allow access to carry out the photographic survey, the proponent must demonstrate in…

Condition 74 DA-2023/334 det. 30/05/2025 Registered club and independent living units

74. Asbestos Removal and Disposal Works involving the removal of asbestos must comply with Councils Policy on handling and disposal of asbestos, and must also comply with the Code of Practice for “How to Safely Remove Asbestos” of the NSW Work Health and Safety Act 2011. Demolition is to be carried out in accordance with the applicable provisions of Australian Standard AS 2601 – The Demolition of Structures. All asbestos laden waste, including bonded or friable asbestos must be disposed of at a waste disposal site approved by the NSW Department of Environment, Climate Change and Water. Upon completion of the asbestos removal and disposal the applicant must furnish the Certifier with a copy…

Condition 34 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

34. BCA Report Prior to the issue of a Construction Certificate, the applicant must notate on the Construction Certificate plans that the BCA Report (Ref 230359 Statement dated 28 November 2024) prepared by Credwell, will be fully complied with. The Performance Solutions identified in Performance based Consulting (Ref: SYD000866-LTR01-D, dated 27.11.2024) must be provided with the Construction Certificate. (Reason: Compliance) PRIOR TO COMMENCEMENT OF WORK PERTAINING TO DA-2024/159 The following conditions of consent have been imposed to ensure that the administration and amenities relating to the proposed development comply with all relevant requirements. All of these conditions are to be…

Condition 61 DA-2023/256 det. 01/08/2025 Development Application

61. Asbestos Sign to be Erected Reference: DA-2023/256 Page 30 of 59 PPSSNH-433 On sites involving demolition or alterations and additions to building where asbestos cement is being repaired, removed or disposed of a standard commercially manufactured sign not less than 400mm x 300mm containing the words “DANGER ASBESTOS REMOVAL IN PROGRESS” is to be erected in a prominent visible position on the site. The sign is to be erected prior to the commencement of works and is to remain in place until such time as all asbestos cement has been removed from the site to an approved waste facility. (Reason: Public Health and safety/Ensure compliance)

Condition 61 DA-2023/256 det. 01/08/2025 Development Application

61. Asbestos Sign to be Erected On sites involving demolition or alterations and additions to building where asbestos cement is being repaired, removed or disposed of a standard commercially manufactured sign not less than 400mm x 300mm containing the words “DANGER ASBESTOS REMOVAL IN PROGRESS” is to be erected in a prominent visible position on the site. The sign is to be erected prior to the commencement of works and is to remain in place until such time as all asbestos cement has been removed from the site to an approved waste facility. (Reason: Public Health and safety/Ensure compliance)

Condition 67 DA-2023/334 det. 30/05/2025 Registered club and independent living units

67. Asbestos Sign to be Erected On sites involving demolition or alterations and additions to building where asbestos cement is being repaired, removed or disposed of a standard commercially manufactured sign not less than 400mm x 300mm containing the words “DANGER ASBESTOS REMOVAL IN PROGRESS” is to be erected in a prominent visible position on the site. The sign is to be erected prior to the commencement of works and is to remain in place until such time as all asbestos cement has been removed from the site to an approved waste facility. (Reason: Public Health and safety/Ensure compliance)

Condition 40 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

40. Licensee Details The name, address and contractor licence number of the licensee who has contracted to carry out the work or the name and permit number of the owner-builder who intends to carry out the work shall be furnished in writing to the Certifier prior to commencement of work. N.B. Should changes be made for the carrying out of the work the Certifier must be immediately informed. (Reason: Information) DURING DEMOLITION, EXCAVATION AND CONSTRUCTION The following conditions are to be complied with throughout the course of site works including demolition, excavation and construction.

Condition 68 DA-2023/334 det. 30/05/2025 Registered club and independent living units

68. Neighbour Notification of Asbestos Removal The applicant/builder is to notify anyone occupying premises in the immediate vicinity of the site, five working days prior to demolition works involving removal of asbestos. Such notification is to be clearly written, giving the date work will commence. As a minimum, this notification is to be placed in the letterbox of every property (including every residential flat or unit) either side and immediately at the rear of the site. (Reason: Public health) DURING DEMOLITION AND BUILDING WORK Conditions from 69 to 94

Condition 72 DA-2023/256 det. 01/08/2025 Development Application

72. Street Number Display During Construction Prior to commencement of work, a street number at least 100mm high shall be clearly displayed on site. The number shall be kept in a conspicuous position and maintained in a legible condition throughout the construction period. (Reason: Improved identification for emergency services) DURING DEMOLITION, EXCAVATION AND CONSTRUCTION The following conditions are to be complied with throughout the course of site works including demolition, excavation and construction.

Condition 62 DA-2023/256 det. 01/08/2025 Development Application

62. Neighbour Notification of Asbestos Removal The applicant/builder is to notify anyone occupying premises in the immediate vicinity of the site, five working days prior to demolition works involving removal of asbestos. Such notification is to be clearly written, giving the date work will commence. As a minimum, this notification is to be placed in the letterbox of every property (including every residential flat or unit) either side and immediately at the rear of the site. (Reason: Public health)

Condition 70 DA-2024/106 det. 24/07/2025 Shop Top Housing

70. Approved plans to be on site A copy of all approved and certified plans, specifications and documents incorporating conditions of consent and certification (including the Construction Certificate if required for the work) shall be kept on site at all times during the demolition, excavation and construction phases and must be readily available to any officer of Council or the Principal Certifier. (Reason: To ensure that the development is in accordance with the determination)

Condition 154 DA-2023/256 det. 01/08/2025 Development Application

154. Ongoing Compliance with the Waste Management Plan The Applicant is required to maintain compliance with the submitted Waste Management Plan (EC Sustainable Waste Plan Demolition, Construction and Operational Phases, Revision B v251024b, 25 October 2024) unless otherwise conditioned. (Reason: environmental protection/waste reduction/public health and safety)

Condition 114 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

114. Retaining Walls and Drainage If the soil conditions require it: (a) retaining walls, complying with the National Construction Code and associated with the erection or demolition of a building or other approved methods of preventing movement of the soil must be provided, and (b) 115. adequate provision must be made for drainage. (Reason: Safety)

Condition 71 DA-2024/106 det. 24/07/2025 Shop Top Housing

71. Control of construction noise (Noise and vibration management plan) During any demolition, excavation or building works, noise generated from the site shall be controlled in accordance with the recommendations of the approved noise and vibration management plan. (Reason: To ensure reasonable standards of amenity to neighbouring properties)

Condition 84 DA-2024/106 det. 24/07/2025 Shop Top Housing

84. Excavations and Backfilling All excavations and backfilling associated with the erection or demolition of a building must be executed safely, and must be properly guarded and protected to prevent them from being dangerous to life or property. (Reason: Safety)

Condition 56 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

56. Excavations and Backfilling All excavations and backfilling associated with the erection or demolition of a building must be executed safely, and must be properly guarded and protected to prevent them from being dangerous to life or property. (Reason: Safety)

Condition 74 DA-2024/106 det. 24/07/2025 Shop Top Housing

74. Suitable Screens In the event of likely emission of dust, noise, waste water or other matter, suitable screens shall be erected during demolition and building work to prevent their emission from the site. (Reason: Maintain amenity to adjoining properties)

Condition 44 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

44. Suitable Screens In the event of likely emission of dust, noise, waste water or other matter, suitable screens shall be erected during demolition and building work to prevent their emission from the site. (Reason: Maintain amenity to adjoining properties)

Condition 68 DA-2024/13 det. 03/12/2024 Mixed Use Development

68. Silencing Devices Sound attenuating devices shall be provided and maintained in respect of all power-operated plant used during demolition, excavation, earth works and the erection of the structure. (Reason: Maintain amenity to adjoining properties)

Condition 47 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

47. Silencing Devices Sound attenuating devices shall be provided and maintained in respect of all power- operated plant used during demolition, excavation, earth works and the erection of the structure. (Reason: Maintain amenity to adjoining properties)

Condition 72 DA-2023/334 det. 30/05/2025 Registered club and independent living units

72. Silencing Devices Sound attenuating devices shall be provided and maintained in respect of all power-operated plant used during demolition, excavation, earth works and the erection of the structure. (Reason: Maintain amenity to adjoining properties)

Condition 77 DA-2024/106 det. 24/07/2025 Shop Top Housing

77. Access to Site During Demolition, Excavation and Construction, access to the site is to be available in all weather conditions, and stabilised to prevent vehicles tracking soil materials onto public roads. (Reason: Environmental protection)

Condition 49 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

49. Access to Site During Demolition, Excavation and Construction, access to the site is to be available in all weather conditions, and stabilised to prevent vehicles tracking soil materials onto public roads. (Reason: Environmental protection)

Condition 50 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

50. Wash Down and Shaker Areas During Demolition, Excavation and Construction, wash down and shaker areas are to be provided with facilities for the collection and treatment of waste water. (Reason: Environmental protection)

Condition 36 DA-2023/256 det. 01/08/2025 Development Application

36. Skips and Bins Rubbish skips or bins are not to be placed on Council’s footpath, nature strip or roadway during demolition and construction unless prior written approval has been granted by Council. (Reason: Safety)

Condition 4 DA-2023/256 det. 01/08/2025 Development Application

4. All demolition and construction vehicles are to be contained wholly within the site and vehicles must enter the site before stopping. A construction zone will not be permitted on Pacific Highway.

Condition 117 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

117. Fire Safety Measures The existing fire safety measures are to be retained and maintained within the tenancies/tenancy during and after demolition. (Reason: Fire safety)

Condition 71 DA-2024/13 det. 03/12/2024 Mixed Use Development

71. Demolition Work AS 2601-2001 Any demolition must be carried out in accordance with AS 2601 – 2001, The demolition of structures. (Reason: Safety)

Condition 77 DA-2023/256 det. 01/08/2025 Development Application

77. Demolition Work AS 2601-2001 Any demolition must be carried out in accordance with AS 2601 – 2001, The demolition of structures. (Reason: Safety)

Condition 77 DA-2023/256 det. 01/08/2025 Development Application

77. Demolition Work AS 2601-2001 Any demolition must be carried out in accordance with AS 2601 – 2001, The demolition of structures. (Reason: Safety)

Condition 73 DA-2023/334 det. 30/05/2025 Registered club and independent living units

73. Demolition Work AS 2601-2001 Any demolition must be carried out in accordance with AS 2601 – 2001, The demolition of structures. (Reason: Safety)

Condition 76 DA-2024/106 det. 24/07/2025 Shop Top Housing

76. Demolition Work AS 2601-2001 Any demolition must be carried out in accordance with AS 2601 – 2001, The demolition of structures. (Reason: Safety)

Condition 46 DA-2024/159 det. 06/02/2025 Residential Flat Buildings

46. Demolition Work AS 2601-2001 Any demolition must be carried out in accordance with AS 2601 – 2001, The demolition of structures. (Reason: Safety)

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.