9,484 conditions across 37 councils · 295 audit errors found across 33 councils · Newcastle, Central Coast, Wollongong added · CB & Lake Mac document checkers live · 37-council directory with LEP links · LEP clause reference + key timeframes ·

Sutherland Demolition Conditions

42 demolition conditions imposed by Sutherland across 3 development applications in our dataset. Demolition conditions set requirements for safely removing existing structures — demolition work plans, asbestos removal and disposal, waste classification, hoarding, and notification of neighbours and authorities.

Condition 15 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

15. Utilities and services Before the issue of the relevant construction certificate or before demolition work commences, written evidence of the following service provider requirements must be provided to the principal certifier OR council (where a certifier is not required): 1. a letter from electricity supply authority demonstrating that satisfactory arrangements can be made for the installation and supply of electricity 2. a response from Sydney Water as to whether the plans accompanying the application for a construction certificate or the plans for the demolition would affect any Sydney Water infrastructure, and whether further requirements need to be met 3. other relevant utilities…

Condition 18 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

18. Hours of work and noise control Hours of work For excavation, demolition, or construction work from 7.00am to 6.00pm on Monday to Friday and 8.00am to 3.00pm Saturdays. No work is permitted on Sundays and Public Holidays. Site work is not to be carried out outside of these times except where there is an emergency, or for urgent work directed by a police officer or a public authority. Noise control DA24/0290 PAGE 9 Demolition, excavation, or construction activities must be managed in accordance with the NSW Department of Environment and Climate Change (now Environment Protection Authority). Interim Construction Noise Guideline (ICNG) 2009, EPA Draft Construction Noise Guideline and…

Condition 18 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

18. Hours of work and noise control Hours of work For excavation, demolition, or construction work from 7.00am to 6.00pm on Monday to Friday and 8.00am to 3.00pm Saturdays. No work is permitted on Sundays and Public Holidays. Site work is not to be carried out outside of these times except where there is an emergency, or for urgent work directed by a police officer or a public authority. Noise control Demolition, excavation, or construction activities must be managed in accordance with the NSW Department of Environment and Climate Change (now Environment Protection Authority). Interim Construction Noise Guideline (ICNG) 2009, EPA Draft Construction Noise Guideline and Australian Standard…

Condition 78 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

78. Notice of commencement for demolition At least one week before demolition work commences, written notice must be provided to council and the occupiers of neighbouring premises of the work commencing. The notice must include: 1. name 2. address, 3. contact telephone number, 4. licence type and license number of any demolition waste removal contractor and, if applicable, asbestos removal contractor, and 5. the contact telephone number of council and 6. the contact telephone number of SafeWork NSW (4921 2900).' Condition reason: To advise neighbours about the commencement of demolition work and provide contact details for enquiries.

Condition 83 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

83. Notice of commencement for demolition At least one week before demolition work commences, written notice must be provided to council and the occupiers of neighbouring premises of the work commencing. The notice must include: 1. name 2. address, 3. contact telephone number, 4. licence type and license number of any demolition waste removal contractor and, if applicable, asbestos removal contractor, and 5. the contact telephone number of council and 6. the contact telephone number of SafeWork NSW (4921 2900). Condition reason: To advise neighbours about the commencement of demolition work and provide contact details for enquiries.

Condition 85 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

85. Demolition work and / or removal of asbestos Asbestos removal signage Before demolition work commences involving the removal of asbestos, a standard commercially manufactured sign containing the words ‘DANGER: Asbestos removal in progress’ (measuring not less than 400mm x 300mm) must be erected in a prominent position at the entry point/s of the site and maintained for the entire duration of the removal of the asbestos. Condition reason: To alert the public to any danger arising from the removal of asbestos. DA24/0346 PAGE 26 DURING DEMOLITION WORK Condition

Condition 2 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

2. It is a condition of the development consent that a sign must be erected in a prominent position on a site on which building work, subdivision work or demolition work is being carried out- a. showing the name, address and telephone number of the principal certifier for the work, and b. showing the name of the principal contractor, if any, for the building work and a telephone number on which the principal contractor may be contacted outside working hours, and c. stating that unauthorised entry to the work site is prohibited.

Condition 2 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

2. It is a condition of the development consent that a sign must be erected in a prominent position on a site on which building work, subdivision work or demolition work is being carried out‐ a. showing the name, address and telephone number of the principal certifier for the work, and b. showing the name of the principal contractor, if any, for the building work and a telephone number on which the principal contractor may be contacted outside working hours, and c. stating that unauthorised entry to the work site is prohibited.

Condition 2 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

2. It is a condition of the development consent that a sign must be erected in a prominent position on a site on which building work, subdivision work or demolition work is being carried out- a. showing the name, address and telephone number of the principal certifier for the work, and b. showing the name of the principal contractor, if any, for the building work and a telephone number on which the principal contractor may be contacted outside working hours, and c. stating that unauthorised entry to the work site is prohibited.

Condition 2 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

2. It is a condition of the development consent that a sign must be erected in a prominent position on a site on which building work, subdivision work or demolition work is being carried out- a. showing the name, address and telephone number of the principal certifier for the work, and b. showing the name of the principal contractor, if any, for the building work and a telephone number on which the principal contractor may be contacted outside working hours, and c. stating that unauthorised entry to the work site is prohibited.

Condition 79 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

79. Demolition work and / or removal of asbestos Asbestos removal signage Before demolition work commences involving the removal of asbestos, a standard commercially manufactured sign containing the words ‘DANGER: Asbestos removal in progress’ (measuring not less than 400mm x 300mm) must be erected in a prominent position at the entry point/s of the site and maintained for the entire duration of the removal of the asbestos. Condition reason: To alert the public to any danger arising from the removal of asbestos.

Condition 14 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

14. Payment of security deposits Before the issue of the relevant construction certificate or before demolition work commences, the applicant must: 1. make payment of $15,000.00 for a security deposit to the consent authority, and 2. if a principal certifier is required to be appointed for the development - provide the principal certifier with written evidence of the payment and the amount paid. Condition reason: To ensure any damage to public infrastructure is rectified and public works can be completed.

Condition 4 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

4. This section does not apply in relation to- a. building work, subdivision work or demolition work carried out inside an existing DA24/0290 PAGE 1 building, if the work does not affect the external walls of the building, or b. Crown building work certified to comply with the Building Code of Australia under the Act, Part 6. Condition reason: Prescribed condition under section 70 of the Environmental Planning and Assessment Regulation 2021.

Condition 83 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

83. Waste disposal verification statement On completion of demolition work: 1. if the demolition work involved the removal of asbestos, an asbestos clearance certificate issued by a suitably qualified person, must be submitted to the certifier within 14 days of completion of the demolition work. Condition reason: To provide for the submission of a statement verifying that demolition has been undertaken appropriately. DA25/0286 PAGE 28

Condition 4 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

4. This section does not apply in relation to‐ a. building work, subdivision work or demolition work carried out inside an existing building, if the work does not affect the external walls of the building, or b. Crown building work certified to comply with the Building Code of Australia under the Act, Part 6. Condition reason: Prescribed condition under section 70 of the Environmental Planning and Assessment Regulation 2021.

Condition 4 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

4. This section does not apply in relation to- a. building work, subdivision work or demolition work carried out inside an existing building, if the work does not affect the external walls of the building, or b. Crown building work certified to comply with the Building Code of Australia under the Act, Part 6. Condition reason: Prescribed condition under section 70 of the Environmental Planning and Assessment Regulation 2021.

Condition 4 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

4. This section does not apply in relation to- a. building work, subdivision work or demolition work carried out inside an existing building, if the work does not affect the external walls of the building, or b. Crown building work certified to comply with the Building Code of Australia under the Act, Part 6. Condition reason: Prescribed condition under section 70 of the Environmental Planning and Assessment Regulation 2021.

Condition 81 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

81. Demolition management plan Before demolition work commences, a demolition management plan must be prepared by a suitably qualified person. The demolition management plan must be prepared in accordance with Australian Standard 2601 - The Demolition of Structures, the Code of Practice - Demolition Work, council’s development control plan and must include the following matters:

Condition 80 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

80. Demolition management plan Before demolition work commences, a demolition management plan must be prepared by a suitably qualified person. The demolition management plan must be prepared in accordance with Australian Standard 2601 - The Demolition of Structures, the Code of Practice - Demolition Work, Council's Development Control Plan and must include the following matters:

Condition 82 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

82. Disconnection of services before demolition work Before demolition work commences, all services, such as water, telecommunications, gas, electricity and sewerage, must be disconnected in accordance with the relevant authority’s requirements. Condition reason: To protect life, infrastructure and services.

Condition 77 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

77. Disconnection of services before demolition work Before demolition work commences, all services, such as water, telecommunications, gas, electricity and sewerage, must be disconnected in accordance with the relevant authority’s requirements. Condition reason: To protect life, infrastructure and services.

Condition 13 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

13. A garbage container with a tight-fitting lid. Condition reason: To provide details of measures for the safe and appropriate disposal of DA24/0346 PAGE 25 demolition waste and the protection of the public and surrounding environment during the carrying out of demolition works on the site.

Condition 87 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

87. Site maintenance While demolition work is being carried out, the following requirements, as specified in the approved demolition management plan, must be maintained until the demolition work and demolition waste removal are complete:

Condition 82 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

82. Site maintenance While demolition work is being carried out, the following requirements, as specified in the approved demolition management plan, must be maintained until the demolition work and demolition waste removal are complete:

Condition 84 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

84. Site preparation Before demolition work commences the following requirements, as specified in the approved demolition management plan, must be in place until the demolition work and demolition waste removal are complete:

Condition 3 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

3. The sign must be- a. maintained while the building work, subdivision work or demolition work is being carried out, and b. removed when the work has been completed. DA25/0286 PAGE 1

Condition 86 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

86. Handling of asbestos during demolition While demolition work is being carried out, any work involving the removal of asbestos must comply with the following requirements:

Condition 81 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

81. Handling of asbestos during demolition While demolition work is being carried out, any work involving the removal of asbestos must comply with the following requirements:

Condition 13 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

13. A garbage container with a tight-fitting lid. Condition reason: To alert the public to any danger arising from the removal of asbestos. DURING DEMOLITION WORK Condition

Condition 3 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

3. The sign must be- a. maintained while the building work, subdivision work or demolition work is being carried out, and b. removed when the work has been completed.

Condition 3 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

3. The sign must be‐ a. maintained while the building work, subdivision work or demolition work is being carried out, and b. removed when the work has been completed.

Condition 3 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

3. The sign must be- a. maintained while the building work, subdivision work or demolition work is being carried out, and b. removed when the work has been completed.

Condition 8 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

8. Details of the equipment that is to be used to carry out demolition work and the method of loading and unloading excavation and other machines

Condition 8 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

8. Details of the equipment that is to be used to carry out demolition work and the method of loading and unloading excavation and other machines

Condition 10 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

10. Details of re-use and disposal of demolition waste material in accordance with council’s relevant development control plan.

Condition 1 DA24/0290 det. 09/05/2025 NPWS coastal protection works - Kamay Botany Bay National Park

1. This section applies to a development consent for development involving building work, subdivision work or demolition work.

Condition 1 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

1. This section applies to a development consent for development involving building work, subdivision work or demolition work.

Condition 1 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

1. This section applies to a development consent for development involving building work, subdivision work or demolition work.

Condition 10 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

10. Details of re-use and disposal of demolition waste material in accordance with Council's Development Control Plan

Condition 11 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

11. Location of any reusable demolition waste materials to be stored on-site (pending future use)

Condition 11 DA25/0286 det. 17/12/2025 Childcare Centre - Gannons Road

11. Location of any reusable demolition waste materials to be stored on-site (pending future use)

Condition 88 DA24/0346 det. 12/06/2025 St John Bosco - Trustee for Sydney Catholic Schools

88. Waste disposal verification statement On completion of demolition work:

Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.