Wollondilly Demolition Conditions
9 demolition conditions imposed by Wollondilly across 3 development applications in our dataset. Demolition conditions set requirements for safely removing existing structures — demolition work plans, asbestos removal and disposal, waste classification, hoarding, and notification of neighbours and authorities.
• The buildings shall not be occupied or used until an Occupation Certificate is issued by the Principal Certifying Authority. • Erection of signs (a) For the purposes of section 80A (11) of the Act, the requirements of subclauses (b) and (c) are prescribed as conditions of a development consent for development that involves any building work, subdivision work or demolition work. (b) A sign must be erected in a prominent position on any site on which building work, subdivision work or demolition work is being carried out: (i) showing the name, address and telephone number of the principal certifying authority for the work, and (ii) showing the name of the principal contractor (if any) for…
(5) The buildings shall not be occupied or used until an Occupation Certificate is issued by the Principal Certifying Authority. (6) Erection of signs (a) For the purposes of section 80A (11) of the Act, the requirements of subclauses (b) and (c) are prescribed as conditions of a development consent for development that involves any building work, subdivision work or demolition work. (b) A sign must be erected in a prominent position on any site on which building work, subdivision work or demolition work is being carried out: (i) showing the name, address and telephone number of the principal certifying authority for the work, and (ii) showing the name of the principal contractor (if any)…
2. It is a condition of the development consent that a sign must be erected in a prominent position on a site on which building work, subdivision work or demolition work is being carried out— i. showing the name, address and telephone number of the principal certifier for the work, and ii. showing the name of the principal contractor, if any, for the building work and a telephone number on which the principal contractor may be contacted outside working hours, and iii. stating that unauthorised entry to the work site is prohibited.
27. Toilet Facilities Toilet facilities are to be provided, at or in the vicinity of the work site on which work involved in the erection or demolition of a building is being carried out, at the rate of one toilet for every 20 persons or part of 20 persons employed at the site. Condition Reason: To ensure site management measures are implemented during the carrying out of site work.
62. Toilet Facilities Toilet facilities are to be provided, at or in the vicinity of the work site on which work involved in the erection or demolition of a building is being carried out, at the rate of one toilet for every 20 persons or part of 20 persons employed at the site. Condition reason: To ensure site management measures are implemented during the carrying out of site work
38. Waste Storage and Processing All waste materials generated during construction works shall be managed in accordance with the approved Waste Management Plan. Copies of tipping dockets shall be retained and supplied to the Principal Certifying Authority. Condition reason: To ensure the correct and lawful handling and disposal of waste during demolition and construction.
34. Site Management All materials and equipment must be stored wholly within the work site. Waste materials (including excavation, demolition and construction waste materials) must be managed on the site and then disposed of at a waste management facility. Condition Reason: To ensure site management measures are implemented during the carrying out of site work.
4. This section does not apply in relation to— i. building work, subdivision work or demolition work carried out inside an existing building, if the work does not affect the external walls of the building, or ii. Crown building work certified to comply with the Building Code of Australia under the Act, Part
1. This section applies to a development consent for development involving building work, subdivision work or demolition work.
Snippets shown for reference only. Verify against the original consent on the NSW Planning Portal.
Demolition conditions in other councils
Newcastle
115 conditions
Ku-ring-gai
81 conditions
Wollongong
78 conditions
Burwood
76 conditions
Cumberland
63 conditions
Sutherland
42 conditions
Willoughby
41 conditions
Bayside
39 conditions
Randwick
30 conditions
City of Ryde
26 conditions
Lane Cove
25 conditions
Inner West
24 conditions
Waverley
23 conditions
Canterbury-Bankstown
21 conditions
City of Parramatta
19 conditions
Campbelltown
18 conditions
Hornsby
18 conditions
City of Sydney
16 conditions
Georges River
16 conditions
Strathfield
16 conditions
Camden
13 conditions
Blue Mountains
10 conditions
Hawkesbury
9 conditions
Liverpool
8 conditions
Fairfield
8 conditions
Canada Bay
7 conditions
Mosman
6 conditions
Lake Macquarie
5 conditions
Woollahra
4 conditions